8408 SHOAL CREEK BLVD
Jurisdiction
AUSTIN FULL PURPOSE
Floodplain — Austin FDFP
Not in a mapped FDFP floodplain per the City layer.
Floodplain — FEMA
Not in a mapped FEMA floodplain per the City layer.
Permits
Recent issued permit events
-
Phase 3 conversion of an existing pre-engineered metal building into a temporary Nissan showroom with a display area customer lounges and sales desk. Phase 2 to Include Mechanical Electrical Plumbing and fire suppression work.
-
Phase 1 Conversion of an existing pre-engineered metal building into a temporary Nissan showroom with a display area customer lounges restrooms and sales offices and Installation of Private Fire Line. - Phase 1 to Include interior build out including electrical paint finishes floor finishes lighting interior partitions and mill-work.
-
Phase 1 Conversion of an existing pre-engineered metal building into a temporary Nissan showroom with a display area customer lounges restrooms and sales offices and Installation of Private Fire Line. - Phase 1 to Include interior build out including electrical paint finishes floor finishes lighting interior partitions and mill-work.
-
Phase 1 Conversion of an existing pre-engineered metal building into a temporary Nissan showroom with a display area customer lounges restrooms and sales offices and Installation of Private Fire Line. - Phase 1 to Include interior build out including electrical paint finishes floor finishes lighting interior partitions and mill-work.
-
Phase 2 Conversion of an existing pre-engineered metal building into a temporary Nissan showroom with a display area customer lounges restrooms and sales offices. Phase 1 to Include Structural Mechanical Electrical Plumbing and fire suppression work.
-
Phase 2 - Installation of underground fireline with fire riser
-
Phase 2 Conversion of an existing pre-engineered metal building into a temporary Nissan showroom with a display area customer lounges restrooms and sales offices. Phase 1 to Include Structural Mechanical Electrical Plumbing and fire suppression work.
-
Phase 3 conversion of an existing pre-engineered metal building into a temporary Nissan showroom with a display area customer lounges and sales desk. Phase 2 to Include Mechanical Electrical Plumbing and fire suppression work.
- Issued permits, last 12 months
- 12
- Issued permits, last 24 months
- 12
- Issued permits with long descriptions, last 24 months
- 12
Zoning
LI
Wildfire WUI flag
No WUI flag on file.
Historic landmark flag
No historic landmark flag on file.
Tree permits
0